on 12-22-2008 8:12 AM
Dear All,
Is there any way we can include the Minimum Order quantity in MRP run.
For example the requirement is 7 Ea.
Lot size is 8
But the MOQ is 16 Ea. (Info Record)
so the MRP run should suggest a planned order of 16 Ea instead of 8.
Plzz guide...
cheers
Hi,
Try your scenario using minimum lot size and maximum lot size values available in MMR.
Regards,
Deepak.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Omair,
It is possible when you set inside the source list "MRP" in the source item to "Record relevant to MRP".Make this setting in the item of the inforecord. During a MRP run, it will use the setting in your inforecord and not the material master.
Award, if useful.
Regards
Rifaie.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.