MOQ

Dear All,

Is there any way we can include the Minimum Order quantity in MRP run.

For example the requirement is 7 Ea.

Lot size is 8

But the MOQ is 16 Ea. (Info Record)

so the MRP run should suggest a planned order of 16 Ea instead of 8.

Plzz guide...

cheers

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 08:20 AM

    Hi,

    Try your scenario using minimum lot size and maximum lot size values available in MMR.

    Regards,

    Deepak.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 22, 2008 at 08:39 AM

    Hi Omair,

    It is possible when you set inside the source list "MRP" in the source item to "Record relevant to MRP".Make this setting in the item of the inforecord. During a MRP run, it will use the setting in your inforecord and not the material master.

    Award, if useful.

    Regards

    Rifaie.M

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.