In time of planned order or PR creation after MRP run factory calender to be followed.Where I can set the factory calender in MRP.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You can create your company factory calendar via transaction code 'SCAL'.

Assignment of the factory calendar by plant is done in transaction code 'SM30 - V_T001W'

This calender is consider as default for MRP also.

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Amitava,

First step is tyou need to create the Factory Calender in Tcode : SCAL and Assign the same to the plant in the menu path shown below :

SPRO : Enterprise Structure -> Logistics General -> Define, Copy , Delete ,Check Plant and Assign the created Factory calender in it.