Hi Experts,
Issue: A Material in MMBE found in QI Stock due to backflushing, but there is no stock physically.
Can anybody share your experience how to resolve this??
Reg,
VRMP
Edited by: Velu on Dec 22, 2008 11:13 AM
Hi
Back flushing is done for the productionorder components. without clearing the stock from quality ,
you might have done the backflush for the order.
so check you can get error in COGI for order (message may be like deficite of material , quantity)
what ever you do physically that has to done in system also(user might have taken out from quality physically, and not completed the UD in system)
so do UD (QA32) for the stock, and goto COGI and process it then stock get consumed.
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Velu,
this could be becasue..the production has entered the used amount..then the unused amount would become backflush amount which is yet to send it back physically.
Regards,
Amol Joshi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi !!
I believe you need to correct the same by physical inventory.....since the qty might have been used up......only the system entry needs to be corrected.
That particular qty might have long been used up.....only the sys entry needs to be corrected.
Regards,
Amol Joshi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Velu,
Please check in COGI if any error movement has taken place for the material. Check with a PP cons
Regards
gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.