Issue: A Material in MMBE found in QI Stock due to backflushing, but there is no stock physically.

Can anybody share your experience how to resolve this??

Reg,

VRMP

Edited by: Velu on Dec 22, 2008 11:13 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Back flushing is done for the productionorder components. without clearing the stock from quality ,

you might have done the backflush for the order.

so check you can get error in COGI for order (message may be like deficite of material , quantity)

what ever you do physically that has to done in system also(user might have taken out from quality physically, and not completed the UD in system)

so do UD (QA32) for the stock, and goto COGI and process it then stock get consumed.

-ashok

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Velu,

this could be becasue..the production has entered the used amount..then the unused amount would become backflush amount which is yet to send it back physically.

Regards,

Amol Joshi

Former Member
0 Kudos

Hi !!

I believe you need to correct the same by physical inventory.....since the qty might have been used up......only the system entry needs to be corrected.

That particular qty might have long been used up.....only the sys entry needs to be corrected.

Regards,

Amol Joshi

former_member186399
Active Contributor
0 Kudos

Dear Velu,

Please check in COGI if any error movement has taken place for the material. Check with a PP cons

Regards

gajesh