cancel
Showing results for 
Search instead for 
Did you mean: 

Purchase order open quantity

Former Member
0 Kudos

Hi,

I am making one report for open purchase order quntity.But there is some problem

In delivery shedule tab of purchase order,If delivery date is in future, that purchase order quantity

also shown by system as open quantity. So whether this open quantity is taken into account or not.

So please guide me.

Thanks and Regards

Anil

Accepted Solutions (1)

Accepted Solutions (1)

former_member529134
Active Contributor
0 Kudos

Hello

Take the open qty as ordered qty (field: MENGE)-delivered qty(field: WAMNG) from EKET table.

Regards

Answers (4)

Answers (4)

Former Member
0 Kudos

Rather than creating a new report u can go through MB5S and check if it fullfills ur requirement.

regards,

indranil

Former Member
0 Kudos

Hi,

The open order quantity means after raising PO the goods yet to recive.

In delivery shedule tab of purchase order,If delivery date is in future, that purchase order quantity

also shown by system as open quantity. Than it will be treated as open quantity.

Former Member
0 Kudos

Hi,

You can also user other transaction for open purchase order quantity.

Enter ME2M t-code.

Then select WE101 in selection parameter option and click on execute button.

Then go in change layout option and take To Be Delivery quantity field in display mode.

You can see open purchase order quantity.

I hope it is useful for u.

Regards,

Mahesh Wagh

Former Member
0 Kudos

As you would like to receive the Qty on the Delivery date,

It must be considered as Open Qty..