Sub-contracting PR from projects

Former Member
0 Kudos

We have several BOMs to be sub-contracted from a project. This BOM header will be manufactured by the sub-contactor and each BOM has a list of raw materials to be sent to sub-contractor.

Please let me know the following

How can a PR be generated from within the project.

1) Settings in material master

2) Internal / External activitiy to be used

3) Where to attach the BOM Header?.

4) How/where would the BOM explosion take place?

Thanks,

Manohar

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

settings in material master would depend on the BOM assemblies

internal or external activity can be used as this would be entered in the component for the activity

BOM header will be attached at the component to an activity

The BOM explosion will also be at that level after attaching the header you can explode it