Sub-contracting PR from projects

We have several BOMs to be sub-contracted from a project. This BOM header will be manufactured by the sub-contactor and each BOM has a list of raw materials to be sent to sub-contractor.

Please let me know the following

How can a PR be generated from within the project.

1) Settings in material master

2) Internal / External activitiy to be used

3) Where to attach the BOM Header?.

4) How/where would the BOM explosion take place?

Thanks,

Manohar

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Dec 21, 2008 at 09:55 PM

    settings in material master would depend on the BOM assemblies

    internal or external activity can be used as this would be entered in the component for the activity

    BOM header will be attached at the component to an activity

    The BOM explosion will also be at that level after attaching the header you can explode it

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.