My Scnerio is MTO..i created one Material and maintained Inhouse production time 5 days.

If i created SO today system is giving 5-01-2009 date as Confirmation date.

How system will caluculate the Scheduline date.......what are the Parameters it will concerns.

Thanks in Advacne

Regards

raj

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 03:13 PM

    Have you checked your factory calendar? How many working days do you have before Jan 5th? Only working days are considered in the in-house production time.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 08:37 AM

    Hi raj,

    1, in the sales order type (VOV8), you can find a field of the Lead time in days. In the field, you can set how many days between an order placed and the proposed delivery date.

    2, you can go to below path in IMG to identify a delivery scheduling for your sales order type and shipping point.

    Sales and Distribution -> Delivery Scheduling and Transportation Scheduling

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.