Error while Executing the Depreciation... in AFAB

Hi experts

We have not at run the depreciation for 2008. If i run the depreciation in AFAB by selecting the following parameters

Company code = ABCD

Fiscal year = 2008

Posting Period = 001

  • Planned posting run

Test run

i m getting the following error.....

According to posting cycle, you should post period 003 next

Message no. AA683

Diagnosis

You cannot post depreciation in the period specified, as this will miss out a posting period.

System Response

No posting can be made in this period.

Procedure

According to the posting cycle, you should post period 003 next. Either enter period 003, which corresponds to the posting cycle, or request an unplanned posting run explicitly for this parameter.

How to solve this problem

Thanks in adcance

A

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 10:52 AM

    Dear ,

    As per your configuratrion,what you have configured system for depreciation whether periodic wise or year wise. You can select unplaned depreciation run,if you have configure period wise run.

    Best Rgds.

    Mani

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 06:28 PM

    This error would come up when the depreciation have been already posted for the said period.

    Are trying this for the first time? or did you run the depr in the previous year? Please explain and also, provide more details.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      When you have run depreciation in a test system some times this date is transported to the test / production system and you can have this problem. there are some SAP note for this.

      You have 3 options

      Look to these note's

      Do for period 01 and 02 not a planned posting but a Repeat run. (do this first in test modus)

      Post period 1, 2 and 3 as one depreciation run (do this first in test modus)

      Can you have a look wath the value is in the table T093D

      Edited by: Paul Annotee on Dec 22, 2008 3:32 PM

      I had put this in an old message:

      -


      Hi,

      This you can have when you did more transports, it takes then the value from your last depreciation run from your development system.

      The values are stored in the the table T093D. You can have a look to it.

      I think you can run the depreciation run for period 1, 2, 3, 4 and 5 as repeat run. Then you get the real values in the correct period. An other option is to run in period 5 cum (1 to 5)

      see SAP note

      https://websmp230.sap-ag.de/sap(bD1ubCZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1065154

      https://websmp230.sap-ag.de/sap(bD1ubCZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=26073

      There are more note's with T093D

      Edited by: Paul Annotee on Dec 22, 2008 3:34 PM

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.