Sir,

In our scenario we are using Repitative Mfg.we are confirming the planned orders with MFBF.

Now my man has mistakenly confirm the order with excess consumption of Raw material.

How to reverse that?

Regards,

A

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Try with MF41

or

Cancel the documents generated against the Movement types. Use the Movement types 261 for component backflush and 261 & 131 for Assembly backflush.

Revert back for Further clarifications.

Regards

Venkat. V

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

You can reverse your entry in MF41