Hi all.

From where we can add the varience % and variance cost in production order.

For e.g. Actual cost of product--100

But i have to add labour cost i.e. 10 RS to production order.

so variance cost--10 rs.

How we can add this.?

Thanks,

Neetu

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 06:55 AM

    Hi Neetu,

    You can add labor as an item to the BOM and it will be available to Production Order.

    Thanks,

    Gordon

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Neetu,

      As suggested by Gordon you have to modify the production order manually for same, other wise better you ask client to pass JE for these compoenent cost as some time practically it becomes difficult to modify each every production order on day to day basis.

      Regards,

      Atul Joshi

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 05:00 AM

    Check thiw WIKI, How to include labour cost in a BOM

    [https://www.sdn.sap.com/irj/scn/wiki?path=/display/b1/howtoincludelabourcostina+BOM.]

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.