Dear all ,

I want to Control the MRP Planning ( MD01 ) only for Demand Orders..

Tell me any User exits / Badi for that Issue..

i checked in this enchancement M61X0001, this is correct or wrong ,,,,

With Regards ,

GJ

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Posted on Dec 20, 2008 at 06:18 AM

    Dear,

    You need to go for enhancement M61X0001 with function al modules EXIT_SAPLM61C_001 and EXIT_SAPMM61X_001 and you can define parameters like MRP controller, MRP Type,Material group etc. It will work for you.

    Regards,

    R,Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 06:22 AM

    Hi GJ,

    If Demand Order is a sale order you are refering to then MD01 will not be useful as planning scope is for a plant or MRP area.

    If it is PIR then you need not use any user exit.

    If you wish to run sale order MRP o a mass scale please confirm.

    Regards,

    Narendra.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Narendra. ,

      Can u explain me , i m not getting properly ,,, i m a ABAPer,,,

      I want MRP planning only for Demand order,,right now MRP planning Demand Order and Stock Transfer Order,,no need to planning Stock transfer order , hw can i will stop the stock transfer order planning ,,,

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 07:17 AM

    Dear GJ,

    Thanx for the reply.

    Mass MRP is run in three modes - normally net change planning is considered in which all the materials that have undergone some change in demand or supply and stock - gain or consumption are considered.

    If your demand is via planning you generate a Planned Independent Requirement PIR.

    STPO is a stock transfer order typicaaly from a plant to a plant.

    And I was refering to a Sale Order which comes from a customer.

    If your STPO is getting generated from a plant you can exclde the plant from planning scope. If not then it can be difficult if for same material you receive a sale order and stpo both.

    OR you can use single level MRP for selective materials.

    Hope this is sufficient.

    Regards,

    Narendra.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Narendra. ,

      thnks for ur reply ,,,

      i have one more doubt,,can u explain me ,,,

      One material having Demand order ,same material having STO (Stock transfer order also ),

      if i run the MRP (MD01) for that material , i need material Planning only for Demand order , not planning for STO (Stock transfer order a),, RIght now MRP planning both orders , i want to stop the planning in STO (stock transfer order ) ,,Is this Possible ? ,,,,,,,,

      with regards,

      GJ

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 08:18 AM

    Hi,

    Can you please tell us from where these demand orders are coming i mean what is driving these demand orders, for example is it coming from sales ?

    Regards,

    Abhijeet Guha

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 08:35 AM

    Dear GJ,

    Yes it is possible.

    Please note that MD01 is not for an individual demand of a material or order.

    It is run at plant or MRP area level.

    For Demand order if it is a sale order you run MD50

    FOr material you run MD02.

    Now if you have a material produced and sold from one plant and same material is sold by another plant where both plants belong to same company then second plant will generate a STPO on first plant i.e. mfg plant.

    So I think if your demand is a sale order go for MD50 - sale order MRP or MD02 --

    I suggest you run MD02, check MRP results and then choose accrdingly.

    Regrads,

    Narendra.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 20, 2008 at 08:40 AM

    Dear GJ,

    You are using MD61, which is creating manual demand of a material in order to create stock of the material.

    You may run MD01.

    I suggest you go thro SAP Library and see for PP- Demand mgmt.- Planning strategies.

    If your demand qty is less than your STPO then system shall generate seperate proposal.

    This is a highly flexible scenario.

    You can set the parameters for considerations in MRP as to which demands should be considered in MRP.

    Regards,

    Narendra.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.