Dear all ,

I want to Control the MRP Planning ( MD01 ) only for Demand Orders..

Tell me any User exits / Badi for that Issue..

i checked in this enchancement M61X0001, this is correct or wrong ,,,,

With Regards ,

GJ

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

Dear GJ,

You are using MD61, which is creating manual demand of a material in order to create stock of the material.

You may run MD01.

I suggest you go thro SAP Library and see for PP- Demand mgmt.- Planning strategies.

If your demand qty is less than your STPO then system shall generate seperate proposal.

This is a highly flexible scenario.

You can set the parameters for considerations in MRP as to which demands should be considered in MRP.

Regards,

Narendra.

Former Member
0 Kudos

Dear GJ,

Yes it is possible.

Please note that MD01 is not for an individual demand of a material or order.

It is run at plant or MRP area level.

For Demand order if it is a sale order you run MD50

FOr material you run MD02.

Now if you have a material produced and sold from one plant and same material is sold by another plant where both plants belong to same company then second plant will generate a STPO on first plant i.e. mfg plant.

So I think if your demand is a sale order go for MD50 - sale order MRP or MD02 --

I suggest you run MD02, check MRP results and then choose accrdingly.

Regrads,

Narendra.

Former Member
0 Kudos

Hi,

Can you please tell us from where these demand orders are coming i mean what is driving these demand orders, for example is it coming from sales ?

Regards,

Abhijeet Guha

Former Member
0 Kudos

Dear Abhijeet Guha,

Thnks for the reply ,,

That Demand Order i will create using T-Code MD61....

Former Member
0 Kudos

Dear GJ,

Thanx for the reply.

Mass MRP is run in three modes - normally net change planning is considered in which all the materials that have undergone some change in demand or supply and stock - gain or consumption are considered.

If your demand is via planning you generate a Planned Independent Requirement PIR.

STPO is a stock transfer order typicaaly from a plant to a plant.

And I was refering to a Sale Order which comes from a customer.

If your STPO is getting generated from a plant you can exclde the plant from planning scope. If not then it can be difficult if for same material you receive a sale order and stpo both.

OR you can use single level MRP for selective materials.

Hope this is sufficient.

Regards,

Narendra.

Former Member
0 Kudos

Dear Narendra. ,

thnks for ur reply ,,,

i have one more doubt,,can u explain me ,,,

One material having Demand order ,same material having STO (Stock transfer order also ),

if i run the MRP (MD01) for that material , i need material Planning only for Demand order , not planning for STO (Stock transfer order a),, RIght now MRP planning both orders , i want to stop the planning in STO (stock transfer order ) ,,Is this Possible ? ,,,,,,,,

with regards,

GJ

Former Member
0 Kudos

Hi GJ,

If Demand Order is a sale order you are refering to then MD01 will not be useful as planning scope is for a plant or MRP area.

If it is PIR then you need not use any user exit.

If you wish to run sale order MRP o a mass scale please confirm.

Regards,

Narendra.

Former Member
0 Kudos

Dear Narendra. ,

Can u explain me , i m not getting properly ,,, i m a ABAPer,,,

I want MRP planning only for Demand order,,right now MRP planning Demand Order and Stock Transfer Order,,no need to planning Stock transfer order , hw can i will stop the stock transfer order planning ,,,

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You need to go for enhancement M61X0001 with function al modules EXIT_SAPLM61C_001 and EXIT_SAPMM61X_001 and you can define parameters like MRP controller, MRP Type,Material group etc. It will work for you.

Regards,

R,Brahmankar