Scheduling semi-finished products

Hi Gurus,

Am working on a food industry implementation.

The scenario is that bulk quantities of product manufactured are packed in cans. Cans are part of BoM-semi-finished material.The cans are produced simultaneously and fed into the packing lines to pack the bulk material into cans.

The requirement is to schedule the can production simultaneous to the finished product production.

When am carrying out backward scheduling the system presumes that the cans should be readily available before packing operation starts - this is not the case.

If forward scheduling is carried out the requirement date is taken as the order start date for both the finished goods as well as the cans.

Have tried to use the lead time offsets in the BoM item details. But not getting the desired result.

Any help on the subject will be appreciated.

Tarang

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Dec 20, 2008 at 06:37 AM

    Hi,

    Try the operation overlapping in operation header in routing. This might solve u r problem.

    shekhar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.