on 12-20-2008 5:39 AM
Dear All,
Here is one scenario :
Actually client wants to maintain fixed lot size of 8 but minimum order quantity 16.so when MRP runs, if requirement is 5 then it should raise plan order of 16 because min order qty is 16 and if requirement is 17 then it shold raise plan order of 24.please guide me how can i cater this csenerio
Hi ahmad,
Give lot size as EX, Minimum lot size as 16 and rounding value as 8. It will generate order proposals in multiples of 8.
Check and revert back for further clarification
Regards
Venkat. V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
U can maintain this one with rouding profiles (go to OWD1).
Shekhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.