Former Member
Dec 19, 2008 at 10:44 PM

overhead-material cost not displayed in cost analysis

620 Views

Hi All,

I have run the following transaction and closed the order but unable to see the overhead-material cost when you check in c002-goto-cost-analysis. Can you help in getting this cost how it display in the cost analysis.

After doing all this still i don't find overhead material ,but labor and direct labor cost is correctly displayed and calculated expect the materila overhead.

i have checked the cost element range and cost variant and planned variant which are properly assinged

OKK4, OPL1,KZS2

1. After Final Confirmation of Order ( Status : CNF) make GR for for order using Tcode : MIGO / MB31 so Production Order Status will be DLV.

2. Then complete the order technically by using Tcode : CO02-- > Functions ( Menu) ---> Restrict Processing -


> Technically Complete. You can carry out TECO for multiple Orders in Tcode : COHV (Mass Processing).

3.Now Calculate Overheads using Tcode : KGI2 - Individual Processing

CO43 - Collective Processing

4.Calculate WIP using Tcode : KKAX - Individual Processing

KKAO - Collective Processing

5.Calculate Variance by using Tcode : KKS2 - Individual Processing

KKS1 - Collective Processing

6.Finally do the settlement of Order in Tcode : KO88 - Individual Processing

CO88 - Collective Processing