cancel
Showing results for 
Search instead for 
Did you mean: 

Consumption based product cost in batches

0 Kudos

HI All...

I am a PP guy.. but have some doubt in product order costing..

We have std BOM where components have been given at the max usage, but normally at the time conusmption they use less(mostly) / more. In costing the difference amount is goin into variance, but client wants the actual consumption of RawactivitiesOH cost should flow to the order rather that std cost from mat master and difference to the variance(PD).

we are managing stock in Batches, so is there any way so that we can capture the actual consumption of mat+act in the order and value of the batch should be updated.

please share ur thoughts......

Edited by: srinivas rapelly on Dec 20, 2008 10:18 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi, Let me try to make things clear. Here, in Production Orders, the actual pricess of Materials consumped are being charged. You need not worry about it. In the case of Activity price and Overhead, first the Production Orders charged at Planned pricess. Then at month end closing activities, you can revalue the activity prices at actual and post the differences to the Production Orders. In the case of Overhead, through actual OH calculation, you can bring in actual overhead. As a whole, the actual cost of the production is being taken into consideration and it is compared against with the standard cost estimate and the differences which is called as Variances are posted for further analysis and control. Trust this helps much! Cheers!

former_member330651
Active Participant
0 Kudos

ashok

nice answer

Former Member
0 Kudos

Hi, Thanks for the compliments but, if possible, make it realistic enough.. Cheers!