i got the following error while assigning the shipping point to the plant

" shipping point "CH" is still assigned to a picking location". i want to know how my shipping point is assigned to a picking location.can any one explain me the concept.

thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

7 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 11:11 AM

    Dear Vamsi,

    I hope I understood your requirement properly,

    Picking location (i.e storage location) will get determined based on these combination in OVL3 transaction which is already mentioned in the earlier response.

    Shipping pointPlantShipping conditions ,so you can have more than one shipping point to the single picking location with combination of different Plant and different shipping conditions.

    Overall meaning is different shipping points can have single picking location.

    I hope this will clear for you,

    Regards,

    Murali.

    Edited by: Murali Mohan.Tallapaneni on Dec 19, 2008 12:11 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 10:56 AM

    Hi

    Chech in OVL3

    regards

    Vamsi Javaji

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 19, 2008 at 11:14 AM

    Hi,

    Check for the Picking rules which define how to determine the automatic picking location determination.

    Picking location is determined in the combination of Storage condition, Delivering plant of the delivery item, Shipping point of the delivery.

    This is a part of standard setting.

    Regards,

    Ranjith

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 11:14 AM

    I think you might have got this error while deleting the assignment. System does not allow to delete the assignment since in OVL3, you would already have a Storage location assigned to the combination of Shipping point, Plant and Storage condition.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 19, 2008 at 11:15 AM

    Hi Mr .Reddy

    If you are defining or creating the new enterprise structure and if you are assigning plant to the shipping point you are not supposed to get this error

    I dont think it is error it is a system message which you can ignore and go ahead

    During delivery process the system picks up storage location automatically thro the rules mainly MALA which we have given in delivery doc types in OVLK

    This MALA rule is storage location determination is based on Shipping pt,delivering plant and storage condition of that material in MMR

    Storage location is the same as picking location

    For this combination we will define a storage location/picking location in OVL3

    This storage location is automatically picked up in delivery doc

    So as the friend suggested check OVL3 also

    Regards

    Raja

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 06:36 PM

    If the issue is Shipping point assignment to Plant, ensure that following configuration is in place:

    1. Maintain Plant

    2. Maintain Shipping point

    3. Assign Plant to Company Code.

    4. Assign Sales Org - Distribution Channel - Plant

    IMG > Enterprise Structure > Assignment > Sales and Distribution > Assign Sales Org - Distribution Channel - Plant

    5. Assign Shipping point to Plant

    IMG > Enterprise Structure > Assignment > Logistic Execution > Assign Shipping point to Plant

    Only after the above configuration at Enterprise Structure Level, it would be appropriate to configure Shipping point Determination. Shipping point is determined based on combination of Delivering Plant

    + Shipping Condition + Loading Group.

    Regards,

    Rajesh Banka

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 05:43 AM

    thank you all

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.