Hi Guru's

I went through many posts related to CM25 profile and scheduling but non of them is matching my query,

My CM25 profile is Customized according to user requirement, when ever the user dispatched multiple order and then tried to shift the scheduling based on the capacity the operations are moving forward, it's just weird that if the operation is moved to a past date the following operation is also moving along with the one that has shifted.

I can understand that to the operation is moving forward due to over caoacity the rest of them are adjusted but if it is scheduled earlier why is the system automatically moving the rest of the operation.

please help me explain the system behavior. Or is it because of my strategy profile config

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 23 at 11:10 PM

    Hello

    I suppose you have activated midpoint scheduling in your strategy profile. Take a look in the information provided below for more details:

    https://help.sap.com/viewer/ca752579215040e487cb292679dd87d4/6.04.19/en-US/4f08b753128eb44ce10000000a174cb4.html

    Regards,
    Caetano