MRP output issue

Dear All PP gurus,

Can you please tell me the solution for this

Hi,

MRP data: maximum data level 6 pieces, reorder point 6 pieces, current situation 3 pieces.

There was on aorder for two pieces from the storage, 1 was already delivered on 04.12.08, the second storage during calendar week 49/2009. I have entered this LT also on the order, so no automatic reminder was generated in SAP.

Now happens the following:

See attached screen shot.

There is a PR created for me about a new order for 3 pieces from the storage!

That is not correct, as we have already gotten 3 pieces from storage and 1 piece comes during week 49.2009.

So there should be only one PR about the new order for two pieces!

Why there is a PR for three pieces?? Is it because of the delivery date of the week 49.2009?? The system obviously does not understand this!!

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 11:54 AM

    Dear All,

    Actually my issue is as below

    One of my client is using reorder point planning with MRP type as Z1 (manual reorder point with external requirements) and with lot size as HB and reorder point as 6 and the stock for the material is 3.

    But when he see in MD04 there is one PR is generated with the qty.3.But he says That is not correct, as we have already gotten 3 pieces from storage and 1 piece comes during week 49.2009.

    So there should be only one PR about the new order for two pieces!

    Why there is a PR for three pieces?? Is it because of the delivery date of the week 49.2009?? The system obviously does not understand this!!

    So kindly tell me that whether it is correct or not or there is any standard setting for the same.

    Thanks in advance,

    Narayan

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear Sree,

      I have checked in lot size date and the settings are as below

      1)lot size HB,Min.lot size zero,max. lot size zero,max. stock level is 6.

      2) i had also checked in OPJJ in that incl.purchace req.POs are ticked properly.

      Kindly suggest what to do ?

      Thanks in advance,

      narayan

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.