Hi

When i am trying to delete a cost center, i get the following error :Usage in table T811C

(T811C: Cycles in Overhead Cost Controlling or Profitability Analysis )

Can you help me in solving the problem

Regards

Venkata NR Chundi

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • Posted on Dec 19, 2008 at 08:46 AM

    Hi,

    You are getting this error because the cost center you are deeting is still assigned somewhere in some cycles (assessment or distribution),so first un assign the cost center from there then delete the cost center system will not give any error.

    thanks

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 19, 2008 at 08:47 AM

    Hi,

    (T811C: Cycles in Overhead Cost Controlling or Profitability Analysis )

    ur cost center is assigned in the above areas so un- assign from there.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 08:48 AM

    hi,

    you are use t.code ks04.

    and delete the cost centre and check standard hieraty option.

    if any problem than discuss me .. than further process are given.

    rohit

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 09, 2009 at 09:49 AM

    No entires in the cost center.

    In Quality server I could not delete it directlly.

    If I change the cost center group to another standard group, I could delete it.

    Why so ?

    Regards

    Venkata Narasimha Rao Chundi

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      The fact whether or not you can delete it, also depends on the validity period that you have chosen. If a cost centre is not assigned during a validity period where allocations cycles exist (using that cost centre) then SAP will allow you to remove the cost centre for that particular validity period.

      Does that answer your question?

      Rene

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.