HI Gurus,

I have 3rd party scenario.

1) I would like to know if it is posiible to restrict creation of PR in sales order, if the customer is credit blocked or if he has a delivery block.i.e PR should not be created on saving the order , if customer has exceeded hiscredit limit or there is a delivery block in customer master.Is there any user exit that I can use?

2) If 3rd party item is marked with reason for rejection , what is its impact on the PR created .Will the PR still remain open.

Thanks and regards,

Nilesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

1. You have controls available for sales orders and deliveries, but not for Prq's or PO's.

2. Rejection of a parent sales order item will delete the Prq.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Nilesh,

1. The behaviour describe is standard system behaviour. The problem is that a third party order is not relevant for delivery. As a result, at no point of document creation will the delivery block be checked.

The delivery block stops only the creation of a delivery.

Creation of the purchase requisition will only be blocked in the case of a credit block on the order. With a delivery block with associated confirmation block, the purchase requisition will still be created.

2. Please check SAP Note 356895.