Budget exceeded WBS

I am creating purchase order for WBS element of amount 76214 USD but getting error Budget exceeded. Details of WBS element is (checked through CJ31) Distributable 807,800.00 USD and Assigned 847,753.97 USD.

Please can you help how to check balance amount in WBS element.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 07:31 AM

    Based on your input, I suppose the Actual Amount is more than the Budget amount. This is because there will be a Tolerance limit set in the system and since the Actual Amount is exceeding the Tolerance limit it gives "Budget exceeded" error message. You can check the tolerance limit set in the following path

    IMG >Project Systems ->Costs ->Budget ->Define Tolerance Limit

    Now you have to increase the budget in CJ30 for that WBS element and try posting the PO against that WBS Element

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.