Hi Team,

I wish to know how to make a change in Calculation Type of Key Figure in Production Environment. I wish to change calculation type from "P" to "S" and also wish to enter Disaggregated Key Figure.

Regards,

Tarun Jha

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 19, 2008 at 04:23 AM

    Hi Tarun,

    Are you in SCM 5.0? If yes, you can go to MSDP_ADMIN, right click on your planning area, select "change key figure settings", click yes when prompted and then change the aggregation type and assign the base keyfigure for aggregation and once you are done, click on generate.

    You should get the popup asking whether you want to make changes, say yes and you are done.

    But as soon as you do this, run the consistency check /SAPAPO/TS_LCM_CONS_CHECK to make sure everything is consistent.

    In some cases, the system does not get set properly then you have no other choice but to take a backup, deinitialize the planning area and then initialize it again and load data back from backup.

    If you are in versions earlier than 5.0, you of course have no other choice but to ake a backup, deinitialize the planning area and then initialize it again and load data back from backup.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      You mean you want to chnage the disaggregation type in Dev and then transport to QA or Production? Since you are in 5.0, Yes. You can do that.

      or also you can just do that in production in "change keyfigure settings" in planning area.

      As I said some times the system may not quite get adjusted as the data is already in there then you have to follow the procedure Arun suggested.

      In theory as per SCM 5.0 documentation, the changes to key figure properties should be effective with out the planning area deinit and initialization. But I have see systems that have some inconsistencies that force you to do the deinit and reinit.

      Make sure that you test this change thoroughly after making the change in production. I mean check whether the data is still being disaggregated by S or is it following P.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.