We would like that at the creation of an equipment with IE01 that a workflow task is created. How can this be done? There doesn't seam to have any standard events through SAP config that could be activated for this object.

Regard

DJ

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Dec 18, 2008 at 07:47 PM

    Hello,

    Do you know what the object is? If it doesn't have any suitable events you can always make a Z version of the object and create your own event. This will then need to be triggered in a user exit.

    regards

    Rick Bakker

    Hanabi Technology

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.