MRP related to batches with expiry date

Hello gurus,

I need your help to understand how to resolve following requirement: perform MRP for batches calculating expiring date. For example, if I have stock enough but it is going to expire I need to plan my replenishment through MRP at a fixed date, is it possible?

Thank you in advance for your collaboration.

Fuffo

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Dec 18, 2008 at 05:04 PM

    MRP will not do such checks (maybe possible thru user-exit).

    You have to take appropriate action with your stocks, e.g. implementing recurring inspection.

    Then you can execute QA07 to create inspection lots and move material into status quality or even blocked stock.

    Once this is done, then MRP can use its standard approach.

    However, if you really have old stocks close to expire, then you should rethink your planning parameters for this material. Just ordering more stock will not solve your issue with old stock, it will just create more stock that will expire later if you dont find a customer or cannot consume it in the window of receiving to expiring.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.