hello,

while creating the PIR for the material after making user settings, system is displaying the message "planned independent requirement not included in MRP".

Regards,

Sarfaraz

Edited by: sarfaraz lodhi on Dec 18, 2008 1:15 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Dec 18, 2008 at 12:23 PM

    Hi,

    Check in User Parameter.Check Box for Version Active is not tick or inactive.That's why system will not consider it for MRP.

    In that case you have to activate that inactive version either manually in MD61 or by MS64 (Copy version)

    Regards,

    Dhaval

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 18, 2008 at 12:27 PM

    Hi,

    1)Check the MRP type of material.It should be relevent to MRP(PD,P1,P2 etc.), not 'ND'.

    2)The version in which you are planning should be active./

    Regards,

    Shailendra

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.