on 12-18-2008 12:15 PM
hello,
while creating the PIR for the material after making user settings, system is displaying the message "planned independent requirement not included in MRP".
Regards,
Sarfaraz
Edited by: sarfaraz lodhi on Dec 18, 2008 1:15 PM
Hi,
Check in User Parameter.Check Box for Version Active is not tick or inactive.That's why system will not consider it for MRP.
In that case you have to activate that inactive version either manually in MD61 or by MS64 (Copy version)
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1)Check the MRP type of material.It should be relevent to MRP(PD,P1,P2 etc.), not 'ND'.
2)The version in which you are planning should be active./
Regards,
Shailendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.