Ck13n / No itemization exists for material -Message no. CK219

hi,

My client production process is Discrete Manufacturing, In routing We Assigned 13 number of operation. We were Doing Cost estimation in CK11n. After costig run, i can get itemization list details. i saved the estimation.

now i enter CK13n, Here system show one POP up.

No itemization exists for material

Message no. CK219

and it not at all displaying Itemization layout

i want to display itemization list layout in CK13n

How can get this????

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Dec 18, 2008 at 07:07 AM

    Dear Prakash,

    If your cost estimate is calculated properly without any error in CK11N and if you have saved the cost

    estimate means ,then in CK13N with a proper costing variant you will be able to see the itemization of

    the cost.

    One small doubt,did you do the cost estimate in CK11N for your FERT?is there any ROH assigned in

    the first level of the BOM or does you FERT contains only HALB?

    Check and revert back.

    Regards

    Mangalraj.S

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.