Hi,

I have a scenario where I need to maintain a default value for Work Durtn [Say 8Hrs] for all PM01 order type. Can we have this Work durtn defulated for the specific order type? What is the customization that needs to be carried? Request you to kindly let me know.

Thanks in advance!

Rgds

Prasad

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

i think there is no customization for defaulting the work duration .the another way will be creating a task list with the standard values and getting into copied in to the order

you can make use of IWO10020-Maintenance order: Automatic inclusion of task list

regards

thyagarajan

Former Member
0 Kudos

Thank you for your answer. I would try out the possibility wrt my scenario.

Rgds

Prasad