How to deactivate creation of Interim MR Result on reversal of Move-out

Hi

I have performed a move-out for an installation on 30.11.2008 and provided the 03 (move-out) read.

Processing for move-out reversal has been configured in the foregound .I have reversed the move-out.

In the move-out reversal on the meter reading tab page system shows that 03 read has been reversed.

On the reversal of 03 (Move-out) read, system automatically created a 09 (interim read without billing)

Is there any customization setting, which can deactivate the creation of 09 reading?

Best Regards

Amit Rastogi

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 18, 2008 at 01:32 PM

    Hi Guys,

    I have found the solution.

    To do so we can get the coding in the exit EDMSUPBI

    Regards

    Amit rastogi

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      We get the same problem when we created a Periodic MRO .

      Look Device Management-> Meter Reading-> Basic Settings-> Define Control Group for Creation of Multiple MR Orders .

      Hope it will help you !

      Michael.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.