on 12-17-2008 2:22 PM
Hi
We want to transfer PR from R3 to SRM. We can see the PR in EPRTRANS table before we transfer it by BBP_EXTREQ_TRANSFER.PR is with standard item category (no account assignment).
But cann't find the PR in SRM.
Any help in this case.
Edited by: Soumik Pradhan on Jan 5, 2009 6:03 PM
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you assigned the proper product category responsibility to the user.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the following
T-code SMQ1, clear the que's.
if any error like - application program error, then check the following
1. whether Plant is replicated properly to SRM or not,
2.this material to extended in the backend to the plant which you are transferrting.
3. Check Org attributes
Hope these answers will do u r job.
Thanks
Sai
Thanks Sai for your response.
As per your suggestion I have done following for my unacount assigned PR transfer :
01. Cleared queues with T-Code: SMQ1 & also confirmed from SRM side (SMQ2).
02.Plants are replicated to SRM correctly.
03.PR's material are existing in plants as defined in PR.
04.Locations are defined to backend Pur. Groups created in SRM.
But requirements are getting stuck up in queue with "ANORETRY" status in T-Code SMQ1.
Any suggestions.