I have created a scenario for Early lot creation for GR against process order. Means when I release the process order, immediately GR lot is generated. Now when I actually do the GR, the system should consider the same lot. But in my case the system is generating one more inspection lot. Can you please help me, why this is happening.
Thanks & regards
Milind
Hi Milind,
Check whether you have posted a different batch to warehouse or you have made a GR posting to a different storage location. In such cases a new lot will be generated for 04 inspection although an early inspection lot already exists.
Please check and revert.
Regards,
Swati
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mlilind,
If you activate inspection type 03,04 in qm view of material master.
then as you release the production order ,inspection lot is generated with inspection type 3 , when GR is made against production order again inspection lot generated because 04 inspection type is active in the QM view
With regards
Yashodhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.