No commitment line item in Purchase requestion after deletion .

Hi SAP FICO experts

Please provide solution for the issue .

User created a line item 20 in the purchase requestion with account assignment u2018Fu2019 (orders ) and deleted this Item 20, usually when deleted ,the line item will be there with deleted symbol, but the line item was not there in the PR

But commitment values for item 20 are shown in PR menu (Environment -> AC Commitment documents ) and in T.code KOB2 (Commitment line items for orders )and in report S_ALR_87013019 (budget/actual commitments)

So user was not able to process new PR with reference to their own budget.so i want to make the commitment value to zero .

one more thing our client has upgraded to ECC6.0 ,will it be the problem for this .

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Dec 18, 2008 at 11:51 AM

    In most of the cases Problem with Commitments are expected for no valid reason. I suggest you to run Program RKANBU01 to fix incorrect commitment. If this is not solved check If you have program ZKAOIDE0 in your system. You can run this program to solve the issue.

    You can check Note [152571|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=152571]

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.