cancel
Showing results for 
Search instead for 
Did you mean: 

CAT5 error BP603 after upgrade to ECC6

Former Member
0 Kudos

When we run CAT5 to transfer the hours (costs) to PS we get the error:

ITEM 001 Ntwk actvty 2086641 FEAS budget Exceeded

Diagnosis:

Budget for WBS element ANS09000.FEAS was exeeded by 120.35 USD in document item 001 Ntwk Actvty 2086641 FEAS.

In the old version this error whas not there and we monitor the errors TC COFC.

I did an other test with a corrrect and this entry. The result was a DUMP!

I found SAP note 96012 - CATS: Messages BP622/BP603 in PM/PS/SM transfer but this for an old version

How to solve this?

Thanks,

Paul

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Your budget seems to have exhausted, check that in report S_ALR_87013558. The cost you are trying to transfer thru CAT5 may be greater than balance budget. Increase the budget by budget update CJ36/37. Release the updated budget if required. Take help from FI consultant.

Regards

Former Member
0 Kudos

I know that we overspend the budget that whas our test case in ECC6. But the program should be run without stopping with an error or an dump. The over budget line's should be solved later with COFC.

When you have thousands of time line's and one line is overspend an budget and you get a dump how you found then the wrong entry?

Former Member
0 Kudos

Hi

Please check the possibilty in confirmation parameters set for the network Txn OPST.If in logs/error handeling if the "Termination for incorrect actual cost"is ticked then it will prevent the postings.

Regards

Answers (2)

Answers (2)

Former Member
0 Kudos

We have implemented SAP notes 1237027 & 1281929

nitin_patoliya
Active Contributor
0 Kudos

Just chekc this Sap notes

Note 570471 - FAQ 2: Confirmations in the Project System

594809 Collective consulting note for PS confirmation

Regards

Nitin