Hello, I'm looking for the function module that will Display a resulting Routing where the VC object dependencies are processed.

There's a similar function for Bom... CS_BOM_EXPL_MAT_V2...

I have standard values(time) in the routing coming from the result of a dependency and this function would tell me the result...

Thanks in advance!

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 15, 2013 at 08:49 PM

    Hi Luc! Hope you're doing well, long time no talk.

    The solution to this post is the function module CUPL_CONFIGURE_ROUTING

    Input fields (PLNTY - Task List Type 'N', PLNNR - Group, PLNAL - Group counter) and finally instance which is the configuration object number, that you could take from MARA or MARC or from VBAP.

    Probably you no longer need this answer, but I wanted to share with others.

    Chris.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 16, 2008 at 01:33 AM

    Hi,

    please check with these Functional Modules.

    CM_DET_MAT_BY_REF_ROUTING Find material by routing/material allocation

    CM_DET_MAT_BY_ROUTING Find material by routing/material allocation

    CM_DET_MAT_BY_ROUTING_OML Find material by routing/material allocation

    Regards,

    Sankaran

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Sankaran, I tried the function you gave me but it's not giving the appropriate time (VGW01).

      By default this field is = 0. There's a VC object dependency on the operation ex: if color = white then time = 4 min.

      I'm getting the correct time when i'm creating a Work order (CO01, CO01S) or when I'm doing a cost roll up. (CK11n).

      What I'M looking is the function that will return the time (VGW01)after the dependency is processed.

      I want to use this function in order to create a report..

      As mentionned previously, for boms, there's a function that's doing this..

      Let me now if you have an idea...

      Regards!

      Luc

  • author's profile photo Former Member
    Former Member
    Posted on Feb 02, 2009 at 04:28 PM

    I'll use a variant in CK11N instead...

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.