ME55 enables an individual release of PR by activating ME54N . It was brought to our attention that

there is a customization procedure to replace ME54N with ME54 . Has anyone any idea , how to do it?

Thanks in advance ,

Haim Schuster

Accepted Solutions (1)

Accepted Solutions (1)

mauro_bianchi
Active Contributor
0 Kudos

Hi Aim,

The call of the purchase requisition is controlled via the

ENJ_CALL_ME53N user parameter.

So if you need to call transaction ME54 instead of ME54N

you have to set the parameter ENJ_CALL_ME53N into SU01 without parameter value.

Regards,

Mauro