Demand management VSE

Nov 07, 2016 at 08:23 AM

43

avatar image

I have Created a material of type fished product as shown below with strategy 50

then I created is BOM and routing and now I assigned requirements on it through MD61

as shown below

and then I run the MRP through MD02

but the result as I understand should be an nonconvertible planned order of type VP but the case is that it shows the result planned order of type LA which can be converted to production order

new-bitmap-image.jpg

Note: there are no sales orders or stock of this material its completely new

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Ramy Sully Mar 07, 2017 at 08:29 AM
0

this was due to some tables in the setting that was not updated automatically due to technical reasons