Dear Friends,

I created a process order for for a quantity of 100. In this process order I am 4 phases. I partially confirmed the first phase for a quantity of 10 only. Then for the next phase system should propose 10 quantity only. But in my case system is proposing the total 100 quantity. Please let me know .. how can we control this. System should propose succeding phase quantity... by default as previous phase quantity only. It should not propose the total quantity. Please let me know... how can we do it???

Regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 15, 2008 at 06:56 AM

    Dear nag,

    check t.code OPK4 with required plant and Order type .

    in

    Edited by: prasad.k on Dec 15, 2008 12:27 PM

    in that operation sequence set as error when operation sequence is not adhered to

    and check .

    regards,

    prasad

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear,

      i also tried for that but qty. is coming fully during goods reciept & also for next operation if partially confirmation is there.

      But if I will give 50% qty. in scrap for last operation then GR qty. is coming only rest of available qty.

      If i will give 50 % qty as a scrap in operation no. 01 even though in operation no. 02 during confirmation full qty. is coming for confirmation.

  • Posted on Dec 15, 2008 at 12:02 PM

    Dear Friend,

    For this you have to define relation between those Phases.Which Should be either FS (Finish - Start) or SS type.

    If you have not define it then first define it.

    Now during Confirmation as per system standard SAP functionality system will propose Order qty. first during Confirmation.But you will find the Confirm yield of predecessor phase during Confirmation of succesor phase by below method.

    - Go to COR6N. select Order and Phase No.

    - Press Actual Data tab.

    - And then Press Enter.

    - Again press Actual Data Tab and see what happen.

    Regards,

    Dhaval

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Dhaval Choksi

      Dear Kodand,

      I also tried & i also faced the same problem initial. But i got the earlier phase confirmed qty.

      You just follow the below steps & for that no configuration is required.

      After maintaining the relation ship you go to COR6N.

      1. Enter Order & Phase & Press Actual Data tab. It will give you a order qty. not as per ur previously confirmed phase qty.

      2. Delete the qty of yield for this phase & enter.

      3. Again press actual data tab. This time u will get the same qty. what u confirmed in earliear phase.

      I hope u will get the right qty.

      Regards,

      mihir mehta

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.