on 12-14-2008 7:32 PM
Hi,
I have a production order of 10 quantites. It has 2 operations 0010 and 0020. Through CO11n I have partially confirmed operation 0010- 3 quantities and 0020 - 2 quantities.
Now due to some reason I want to postpone the execution of the production order to next week.How to do this?? Can it be done in CM21 by dispatching the remaning operations 0010 and 0020 to a different date? Buy it is already partially confirmed. What is best way to do this?
Regards.
not solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes, you can do this by Capacity Levelling in CM21, but there will be a difference in Plan Vs Actual dates of execution of the process. In you case, actuals seems to be taken for processing before the planned Scheduled dates of operation. Also, you can mention the reason for datas postpond in reason for variance.
Hope this helps..
-Thaila Shree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.