Dear Experts,
We have confirmed 100 nos of finished product with completion indicator in the goods movement. We also cancelled the confirmation with the completion indicator . But the production order still showing the delivered quantity as 100 nos and not allowing us to do confimation and GR. We also removed the delivery completed indicator. Please explain.
Thanks.
Hi,
check in COGI for Incorrect Goods movement for that Order.May be due to some reason Goods movement gets interrupted or not posted.In that case you can find it in COGI.Find the reason behing it by pressing Bell (Warning) Icon clear it and re post it.
For future prospects do one settings in your Confirmation Profile.
Go to OPK4 select your Plant and Order type and in Detail screen go to General Individual Entry Tab and here Activate Check box of Error Handling in case of wrong Goods Movement and Act. Costs.This will terminate the Confirmation in both cases.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Pls check error in COGI.
Cancle the MBST document if posted.
Kindly reverse the GR for production order.
Again do the GR and while doing GR select Del.Completed.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.