on 12-12-2008 11:22 AM
Hi,
My abaper has created a new pricing requirement which is active. I can see it in VOFM but can not see the same in pricing procedure in requirement column.
need help,
Thanks,
pramod
Hi,
Have you assigned application to routine?
Application should be blank or V.
Regards,
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pramod,
In T. Code: VOFM
From Menu-Bar,
Requirements --> Pricing
Here, check whether your Z-Routine for Pricing is being "Listed". If Listed, whether its is being "Activated". Also, "Application" attached to your routine is correctly assigned (say, V)
Bes Regards,
Amit
Note: I have notice that only those Routines, lised with Application "V" will be available in Transaction V/08, under Column: requirement. Others, of any kind (say, Application - M, MS, F etc.. are not available).
The idea is, Your Pricing Procedure Application (in T. Code: V/08, you may see Application, under which PP is maintained), and Routine Application must be same.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.