Hi Experts,
I would like to know on how to create and assign an Investment program in Budget profile.
Is an investment program mandatory for Investment Project and for New Product Development Projects?
Will there be any implication if we do not assign an Investment program in Budget profile settings in OPS9.
Please suggest & advise.
Thanks & Regards,
Kabir
if you enter program in OPS9 then you will only be able to budget from IM in the whole WBS hierarchy from the link point - this is OK if you do wnat to budget for opex in your project
however if you want to have a project with capex budget from IM and opex budget directly in WBS (txn CJ30) then leave IM program in OPS9 blank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.