Investment Program in Budget Profile

Former Member
0 Kudos

Hi Experts,

I would like to know on how to create and assign an Investment program in Budget profile.

Is an investment program mandatory for Investment Project and for New Product Development Projects?

Will there be any implication if we do not assign an Investment program in Budget profile settings in OPS9.

Please suggest & advise.

Thanks & Regards,

Kabir

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

if you enter program in OPS9 then you will only be able to budget from IM in the whole WBS hierarchy from the link point - this is OK if you do wnat to budget for opex in your project

however if you want to have a project with capex budget from IM and opex budget directly in WBS (txn CJ30) then leave IM program in OPS9 blank

Former Member
0 Kudos

Hi Virendra,

Thank you for the reply.

Please clarify this in your 2nd sentence, "if you do wnat to budget for opex in your project" . Is it do or do not want to?

Awaiting your reply.

Regards,

Kabir

virendra_pal
Active Contributor
0 Kudos

it should be if you do not want to budget for opex

Former Member
0 Kudos

Thanks virendra. SOLVED.

Answers (0)