in the projects,
we dont want to allow user to confirm more hours than planned hours.
Pls suggest.
Thanks
txn OPST
set confirmation parameters with work and duration deviation = 0
set up std workflow for work/ duration deviation
if anyone does ignore the warning and continues with the confirmation at least you will get a message
this is std SAP no development is needed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I am not sure if there is any Config. You can make use of user exits EXIT_SAPLCORF_009 and EXIT_SAPLCORF_007. This can enable you to compare planned and actual work hours.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.