on 12-11-2008 11:42 AM
Hi, I need some help.
My problems is the following.
In my system I have 2 controlling areas.
In OKTZ two cost component structures are defined - C1 for CO area 1000 and C2 for CO area 2000.
I have created drilldown reports for both in KKO0.
When I save in OKN0 the control parameters Cost component structure C1 to be default, the reports in Controlling area 2000 are not filled with data as they use CCS C2.
Could someone give me an idea what can I do?
Thanks in advance!
Hi,
We can use one Cost component structure for two controlling area , u have to assign the GL account for that 2 company code as per cost component.
In CCS Important is assignment of organization Units.So, check u have maintain or not.
Regards,
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Cost Component Structure are not assigned directly to Controlling Area. It depends on the cost elements of respective controlling area to the be assigned to the respective Cost components in the CCS. Further you are assigning in the Costing variant, company code to the CCS with the validity date,Last but the least you need to activate both the CCS.
When you execute the Std cost estimate based on the Costing variant, CCS is assigned and the same is populated in Product Drilldown reports as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.