Can any one suggest me how to create a Order BOM.

Quantum.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Quantum,

Already explained, by other members, however, you may have a look in to:

[BOM|]

[BOM - Concept|]

[Table for BOM Fields|http://www.sap-basis-abap.com/sappp007.htm]

[Sales BOM|http://www.sap-img.com/sap-sd/sales-bom-implementation.htm]

Best Regards,

Amit

Note: Few Key-points, to remember:

1. Item Cat. Group enters as ERLa/ LUMF, for main Material.

2. While creating BOM, T. Code: CS01, BOM Usage as "5 - Sales and Distribution"

3. Main Material Plant (T. Code: MM01/ 02) and BOM-Plant (T. Code: CS01/ 02), must be same.

Former Member
0 Kudos

Hi Guys

Thanks for all your reply. I could able to know many things on BOM now.

But Order BOM is not resolved and still in ?.

i am talking about cs61 tcode not cs01.

My issue is after copying mail BOM in to Order BOM and saved it. But still MRP run considering the main BOM.

Please give some inputs on CS61 Tcode and MRP relation.

Lakshmipathi
Active Contributor
0 Kudos

Check this help link

[Order BOM |http://help.sap.com/saphelp_47x200/helpdata/en/41/c18342350411d3b460006094b9d648/frameset.htm]

thanks

G. Lakshmipathi

former_member204513
Active Contributor
0 Kudos

Dear Quantum,

These are steps to create Sales BOM

1.You create master data for the header item as well as sub items with itemcategory group ERLA or LUMF through MM01 transaction.

2.You create Sales BOM for those material through CS01 transaction.

Go to CS01 enter header material Plant and BOM usage as 5-Sales and distribution.

3.Check the item category determination for the header material as well as sub items through VOV4 transaction.

4.Go to VOV7 transaction select header material itemcategory then go in to the detail here you find the fields Structure scope and Application under Bill Of Material/Configuration tab,maintain these fields as

A -Explode single-level bill of material and SD01-Sales and distribution.

5.Maintain proper stock

Now you can create sales order for that BOM material through VA01 transaction.

I hope this will help you,

Regards,