More than six Std. Value Key

Former Member
0 Kudos

Greetings,........

how to define more than six value under one standered valu key.

Accepted Solutions (1)

Accepted Solutions (1)

former_member335796
Active Contributor
0 Kudos

Hi,

With the Same Std. Value key it is not possible to have more than 6 Std. Values.

But, with a different stanadrd value key(in addition to the first one) and a Dummy work center (for the Original one) we can manage the situation...

Regards,

Siva

Former Member
0 Kudos

thanks for your reply..

will u please tell me the procedure to define dummy work center and pricedure assigned in routing to prodcition order .

former_member335796
Active Contributor
0 Kudos

Hi,

Routing

0010 Workcenter (XYZ) Control key PP01

0020 Dummy Work Center (XYZDummy) Control key PP01

Now for the XYZ workcenter you will have 6 standard values and assigned to to the first Operation.

Remaining Standard values say 7, 8 and 9 will be assigned to the Std. Value key for workcenter XYZ Dummy.

Now create Order with this Routing, confirm both the operations Values will be captured as intended.

Hope this clarifies..

Regards,

Siva

Answers (1)

Answers (1)

Former Member
0 Kudos

HI

standard SAP given optiononly for 6.

if you want more as above suggested you need to go with one more work cntre series

-ashok