Why this WBS grouping is used for ?? , what is the main purpose of this ??

Thanks ,

Dhruv Kumar Malhotra

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 10, 2008 at 07:50 AM

    Hi,

    A Grouping WBS element is a WBS element that has valuated project stock on which the requirements from several WBS elements are grouped together for materials requirement planning (MRP).

    You determine that a WBS element is a grouping WBS element by making the following settings for the Grouping WBS element field on the WBS element detail screen (on the Basic data tab page in the standard system)

    If this WBS element is to be the grouping WBS element for all components assigned to the WBS elements that have been assigned to this grouping WBS element, enter Grouping WBS element for all materials (1).

    If the material components assigned to a WBS element are to have different grouping WBS elements, enter Grouping WBS element for selected MRP groups (2). This could be the case, for instance, if you want to plan electrical and mechanical parts separately.

    The valid grouping WBS element is then selected on the basis of the MRP group and plant of the material.

    If you have set the Automatic requirements grouping indicator in the project definition of a project, only one grouping WBS element is allowed in the project. In this case the first WBS element on level 1 is suggested as the grouping element. You must then have defined the WBS element as Grouping WBS element for all materials (1).

    Regards,