cancel
Showing results for 
Search instead for 
Did you mean: 

Costing of Production Orders

Former Member
0 Kudos

Dear Gurus,

My client requirement is that , always the planned costs need to be captured in to the productin order while confirming,irrespective of the actual costs.

What settings should i do , to enable the system to perform the same?

Best regards,

K.kumar.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member335796
Active Contributor
0 Kudos

Hi,

This can be achieved, if we don't change activities and component quantities during confirmation.

It means the Planned and actual costs are same. So, there will be no variance.

But why?

Regards,

Siva

Former Member
0 Kudos

Hi,

We will not alter the components or activities. But sometimes(most of the times) the time consumed for an (production time) activity is more than that of the planned time. Hence Variance will occur definitely.

My client is not interested in capturing this.He want the planned activities to be the final one, irrespective of variation in time(activity).

regards,

K.Kumar.

former_member335796
Active Contributor
0 Kudos

Hi,

If you don't change the Activity times then how it is going to impact?

Is there any PDC interface is used to capture the Operation Times??

Regards,

Siva

Former Member
0 Kudos

Hi,

What I meant is,

Planned Start time : 8 AM on 10th Dec,2008

Planned End time : 2PM on the 10th Dec,2008

Actual Start time : 8 AM on 10th Dec,2008

Actual End time : 6 PM on 10th Dec,2008

Here how will we accout for the 4 hrs.? Client donot want this(due to reasons best known to the client, though this is not advisable).

Best regards,

K.Kumar.