on 12-10-2008 6:33 AM
Dear Gurus,
My client requirement is that , always the planned costs need to be captured in to the productin order while confirming,irrespective of the actual costs.
What settings should i do , to enable the system to perform the same?
Best regards,
K.kumar.
Hi,
This can be achieved, if we don't change activities and component quantities during confirmation.
It means the Planned and actual costs are same. So, there will be no variance.
But why?
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
We will not alter the components or activities. But sometimes(most of the times) the time consumed for an (production time) activity is more than that of the planned time. Hence Variance will occur definitely.
My client is not interested in capturing this.He want the planned activities to be the final one, irrespective of variation in time(activity).
regards,
K.Kumar.
Hi,
What I meant is,
Planned Start time : 8 AM on 10th Dec,2008
Planned End time : 2PM on the 10th Dec,2008
Actual Start time : 8 AM on 10th Dec,2008
Actual End time : 6 PM on 10th Dec,2008
Here how will we accout for the 4 hrs.? Client donot want this(due to reasons best known to the client, though this is not advisable).
Best regards,
K.Kumar.