issue with Project Status change date

Former Member
0 Kudos

Hi All,

We have a project with status REL.

Now user will change the status as TECO.

I would like to know on which date the user has changed this status from REL to TECO.

How to get this date on which the status of the Project has changed as TECO?

Regards

Pavan

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

Go to Cj20n --> click on the WBS / netwrok activity (for which you want to see the status change track.) --> Edit menu > Status> system/ user status ( system will take you to change status screen ) --> go to extra menu --> change document --> all ( system will take you to change docuemnts in status management ) use 'all changes' & 'history' tabes for your analysis.

Regards

Nitin

Edited by: Nitin Patoliya on Dec 9, 2008 8:40 PM