Hi Friend,

File Merging:

==========

I wonder why the receiver step not taking the " Use Correlation" or "Activate Correlation" value even after creating the correlation list and check(F7) the same.

At receivers step in Graphical Definition(BPM) I can see the red question mark against Activate correlation value, I can see the value to choose. But when I choose the value and save the value does not stay there it disappears.

I feel that the correlation list value is not been activated and hence unable to use it for the receivers steps.

When I activate the Integration Process, below is the error message appears.

Activation of the change list canceled 
Check result for *Integration Process kanchuBPM_IS | http://kanchuBPM_merge.com:  *
Step does not use any correlations  
Step does not use any correlations

One more information:

Used steps in BPM....

Fork :  Fork1
Receive: Receive1
Receive: Receive2
Transformation: Transformation1
Send: Send1

Here the problem is at Receive1 and Receive2 steps. - Unable to choose the correlation value created.

Regards,

Venkat Ramana K.