Request you to please guide whether we can exclude the Material Quantity in Pipeline which is yet to be received against any Purchase Order raised to any vendor for Procurement from the scope of MRP.

Also request you to please guide whether we can exclude some Batch Stocks from the scope of MRP Process.

We are using VB as MRP Type.

Please guide.

Thanks and Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 22 at 07:40 AM

    I have seen that Storage Location can be used to avoid any stock to get considered in the MRP Process. But for the first query related to Quantity in Pipeline please reply. Thanks

    Add comment
    10|10000 characters needed characters exceeded

  • May 22 at 11:53 AM

    Why do you use MRP type VB for your pipeline material. Usually pipeline material is always available as it has no stock, you just turn the tab and the material is flowing. You do not even do a receipt against a PO, you just consume and settle.

    Add comment
    10|10000 characters needed characters exceeded

    • Jürgen Lins Mahavir Vashishth

      PIPEline material is very specific, some functions are even hard coded.

      There might be ways for normal materials, but you are using a pipeline materials wrong, so I doubt that there are many people around who also use the pipeline material like you do and could share their experience. Looks like you have to try it with normal material and then you would need to share a bit more information about your MRP settings and the stock situation