i am adding internal processing activty in my proj for tracking amount of work confirmned only.. and not for costing, cap pllnning purposes,,,, i can provide a report of cnfmations to ma customer, but the demand rite now is like this as follows....

suppose the work is 100 kms digging... my first km is named position 1200, after 10 km i would be at position 1210 and so on... can we achieve this in ps ... i am thinking to feed this data in some user field in wbs and get some abap report to achieve the same.. can i do this ... or is there some other solution.... also i am not able to see remaining work in the report.. how to do the same.....pls assist

Rahul

Accepted Solutions (0)

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

This can be achieved by using partial confiration, Final confirmation & degree of processing.

The degree of processing of a partial confirmation inidates to what percent the activity has been processed. System calculate degree of processing from the proportation of actaul amt of work that has already been confirmed for an activity to it's planned or forcasted total work.

you can also define alternative degree of processing manually in confirmation.

you can also use workcenter actaul work & remaining work ( forcasted ) fields in partial confirmation to document which workcenter has performed which degree of work & how much still to be performed.

you can use CN48N report for viewing the confirmation.

Prerequisite for Actvity confirmation is

the activity must be released

control key of the activity must allow the confirmation.

In customising you must have to defined the confirmation parameters which controlls the properties of the confirmation.

Regards

Nitin

Former Member
0 Kudos

how does the system calculates degree of processing..... i am not able to see remaining work in confirmation overview screen,..... i have cnfrned 50km out of 200km....

nitin_patoliya
Active Contributor
0 Kudos

Degree of processing linked with project progress.

Please go thoug this link.