How to restrict Production order with status NMAT from release in SAP

Dear All

I have scenario where in absence of BOM ,production order are created for status CNC ( Cost Not Calculated ) and NMAT ( No Material assigned) .We understand that this is due master data creation not happening on time .

In such scenario ,we wish to avoid such orders with status NMAT from further processing ie Order Release ,so that further activities could not be processed further .

Thanks in advance

Upinder

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 21 at 09:49 AM

    Hi

    You can use BADI WORKORDER_UPDATE

    Method "AT_RELEASE"

    The structure COBAI_S_HEADER_DIALOG has CAUFVD structure

    The CAUFVD structure has STTXT field (system status)

    So you are able to read system status.Please have an error message when it has NMAT.

    Hope this helps

    BR

    Raghavendra


    Add comment
    10|10000 characters needed characters exceeded

  • May 21 at 09:52 AM

    Upinder,

    You can configure user status for this. You will find many documents related to the same in SCN.

    Rajen